CURRENT
WATER PROBLEMS
A more detailed explanation will be
posted on the blog in Finnertys shop window in the coming days; brief
overview below for those who didn't bother to attend meeting
At the start of July problems with the
water quality were reported, tests have taken some time to arrange.
The initial suspicion was contamination (from either septic tank,
silage or slurry) – hence flushing. Further investigation revealed
that the cause is a seasonal low, leading to metallic contamination,
probably iron & manganese (test results will confirm), so main
flushing stopped.
We
remain on a boil notice – as we have been for many years – but
otherwise the current problems have been classified as unpleasant but
not unhealthy.
These
problems can be treated,
indeed they are shared with many public water sources, the problem is
that we did not know or expect that we needed to do it. All the work
that has been done was
needed & will
be of benefit, but until we get the final piece of the jigsaw (which
we didn't know we needed) in place, the picture is not complete.
Even
with the change in the weather, it is not certain how long the
problem might go on for, and the although there
is a fix,
it will take time (5-6 weeks minimum)
to implement, so we are pursuing an interim solution of pumping water
from the main Castlelodge river which, finances permitting, could be
up & running in a matter of days.
SCHEME
FINANCES
In the last bulletin, an appeal was
made for those members in arrears to bring their accounts up to date;
this did not happen and the finances have in fact got worse. Not only
has this continued to slow the needed upgrades – without which will
not come off boil notice – but we can barely afford our overheads
(such as ESB bill for pumping).
It
is unfair to start a new collection from those good enough to pay on
first asking when so many still owe from the last.
In
addition to contributions owed, we may have to ask members to make an
additional one time contribution of €125 to fund the interim
solution above if we do not receive funding from the council – which we
should hear about by Monday.
We will be able to fund the full
solution from normal contributions, and this years contribution will
be collected in Oct-Nov, tbc.
Next
Meeting
A further meeting will be held in 4-6
weeks, date TBC and this will be designated as the AGM, at which some
votes concerning key decisions about the schemes future will be made.